Tri-Pack Films Project
- Location:
Plot# G-1 To G-4, North Western Industrial Zone,
Port Qasim, Karachi. - Project:
Construction of 1653 Plant Building,
Gas Power Plant and CPP Line-2 Building. - Scope of Work:
Construction of Gas Power Plant,
1653 PTB Plant and CPP-Line-2 Building at Plot # G-1 To G-4,
North Western Industrial Zone Port Qasim Authority,
Karachi. (Packages Group) - Client:
Tri-Pack Films Limited (Packages Group) - Engineer:
Progressive Consultants (Pvt.) Ltd - Current Value:
663 Million Rupees. - Starting Dated:
September 2011 - Completion Date:
December 2013
Tri-Pack Films Limited is building a new Biaxially Oriented Poly Propylene Plant (BOPP) with a capacity of 40,000 metric tons. This shall double the combined BOPP production capacity of the company from present 30,000 tons per annum to 70,000 tons per annum.
ACL’s scope of work includes:
- Construction of 1653 PTB Plant Building
- Utilities Areas
- External Sewerage
- Water Supply
- Fire Fighting System
- Road & Storm Water Drainage
- Gas Power Plant Building
- H.R Chillers
- Cooling Towers
- Control Room and Transformer Room
- CPP-Line-2 Building