skip to Main Content

Tri-Pack Films Project 2

  • Location:
    Plot# G-1 To G-4, North Western Industrial Zone,
    Port Qasim, Karachi.
  • Project:
    Construction of Line 5, Powerhouse, RO plant, and ancillary buildings.
  • Client:
    Tri-Pack Films Limited
  • Engineer:
    Ahad and Associates
  • Current Value:
    Rs 600 million.
  • Starting Dated:
    September 2022
  • Completion Date:
    March 2024

Tri-Pack Films Limited is expanding its BOPP production capacity at its plant in Port Qasim with the addition of line 5.

ACL’s scope of work includes:

  • Construction of line 5 plant building
  • Utilities Areas
  • External Sewerage
  • Water Supply
  • Fire Fighting System
  • Storm Water Drainage
  • Power Plant Building
  • RO pump room and tank
  • Cooling Towers
  • Control Room and Transformer Room